NSW / DBPA
DBPA in NSW: what it means for remedial building work
A practical guide to the Design and Building Practitioners scheme, regulated designs, practitioner roles and planning remedial work in NSW.
The Design and Building Practitioners Act 2020—often called the DBPA or DBP Act—affects how many NSW remedial projects are designed, documented and delivered. Owners should establish the applicable pathway early.
NSW guidance checked: 13 November 2026. This article discusses the design, registration and declaration scheme. The application of other provisions and other legislation needs to be considered separately for each project.
Which existing buildings are covered?
The DBP scheme applies to remedial work on class 2 buildings, including mixed-use buildings with a class 2 part, subject to exclusions and the relevant emergency provisions. Class 2 generally includes apartment buildings.
The scheme expanded to certain new class 3 and 9c buildings from 3 July 2023. NSW has deferred its application to alteration, repair and renovation work on existing class 3 and 9c buildings until 1 July 2028. Establish the building classification and type of work rather than assuming the same rule applies to every site.
A builder’s licence and DBP registration serve different roles
A contractor licence under the Home Building Act and registration under the DBP scheme are separate requirements. Where the scheme applies, the head contractor needs the relevant building practitioner registration. Regulated designs must be declared by design practitioners with the appropriate registration and authority for their work.
For owners, the practical question is who is responsible for each design, declaration and lodgement—not simply whether a company describes itself as a builder or consultant.
Resolve the design before the related work starts
Work involving a regulated building element or Performance Solution can require a Construction Issued Regulated Design (CIRD) and a design compliance declaration. Relevant documents must be lodged on the NSW Planning Portal before the related building work starts, unless a specific exclusion or lawful exception applies.
The government guidance calls for construction-ready designs rather than draft or shop-drawing substitutes. The team should have enough detail to understand the work and coordinate the different design disciplines.
Check exclusions carefully, particularly for waterproofing
Some work is excluded under the DBP Regulation. Development that is exempt under planning rules does not automatically settle the DBP question for waterproofing.
The single-dwelling wet-area exclusion has specific conditions: the waterproofing must result from alterations to a bathroom, kitchen, laundry or toilet; the alterations must be exempt development; and the work and agreement must relate only to one dwelling. The project team should check the full regulation against the actual scope.
Plan for variations and completion records
A change involving a regulated building element or Performance Solution can require updated designs and declarations before that changed work proceeds. A variation process should therefore allow time for both design review and construction decisions.
At completion, the building practitioner has declaration and document-lodgement obligations. These can also apply where an occupation certificate is not required. Agree the required close-out documents and responsibilities at the start of the project.
Useful questions for an owners corporation
What building classification and regulatory pathway has the team identified?
Which practitioners will declare the designs and lodge the documents?
What design information is needed before the tender and before construction?
How will concealed conditions and design changes be managed?
What records will the owners receive at completion?
These questions help turn compliance obligations into a clear project plan and a more useful conversation with the design and construction team.
Further reading
NSW Government — building classes and practitioner roles
NSW Government — design practitioner obligations
NSW Government — building practitioner obligations
Building Commission NSW — updated regulatory commencement dates