NSW / NCC 2022
NCC 2022 in NSW: potential impacts on remedial projects
How the applicable code edition, wet-area details and existing building interfaces can affect the scope, cost and programme of remedial works in NSW.
For an owners corporation planning repairs, the relevant question is how the applicable building requirements affect the actual work being proposed. That can influence the design, price and programme before construction starts.
NSW position checked: 13 November 2026. NSW Government currently identifies NCC 2022 Amendment 2 as the current edition. It commenced on 29 July 2025. NSW has announced adoption of NCC 2025 from 1 May 2027.
Start with the correct edition and pathway
NCC 2022 was generally adopted in NSW from 1 May 2023. The relevant edition for a particular project depends on its approval and certification circumstances, including applicable transitional arrangements. Ask the project designer and certifier to confirm the edition and NSW variations that apply.
Compliance can follow the Deemed-to-Satisfy provisions, a properly developed Performance Solution, or a combination. The project documents should identify the chosen approach so it can be allowed for in the tender and carried through to construction.
Wet-area levels can affect more than the tiles
The Building Commission NSW Building Defects Library identifies changes to floor-fall requirements in NCC 2022. It also discusses wet-area construction, drainage and waterstop detailing. When rebuilding a bathroom, the designer should consider these matters together with the existing structure and finished floor levels.
A practical consequence may be a need to review screed thickness, floor waste positions, doorway levels or adjoining finishes. These are matters to investigate before pricing the work; their extent depends on the particular design and site conditions.
Existing doors and balustrades need a coordinated scope
Remedial works can interact with parts of the building that will otherwise remain in place. NSW guidance expects the designs to clearly show the boundary between new remedial work and retained building elements.
For example, a balcony waterproofing design can affect the treatment of an existing sliding door. The NSW guidance distinguishes between a compliant repair that can be designed without interfering with that door and work that does interfere with it. The design team should resolve the relevant interfaces and any identified safety issues before the scope is finalised.
Check the NSW sustainability requirements
NSW residential projects also have a state-specific BASIX framework. Its standards were updated from 1 October 2023. The applicable sustainability requirements depend on the type of development and approval; a new-home requirement should not simply be assumed to apply to every repair.
Potential effects on the budget and programme
In our view, the most useful early allowance is time to resolve the design and scope. A tender should make clear:
Which existing elements will be retained and which will be altered.
What investigations or opening-up are needed before the final detail can be settled.
How the waterproofing, drainage and adjoining components will connect.
Who is responsible for design coordination, inspections and project records.
How a change discovered on site will be assessed and priced.
These are project-planning considerations rather than a prediction that every NCC change will add cost. A clearly documented scope gives owners and tenderers a better basis for comparing proposals.
Further reading
NSW Government — how to comply with the NCC and current adoption dates
Building Commission NSW — floor waste and fixture requirements
Building Commission NSW — Building Defects Library
NSW Government — remedial building work in regulated buildings
NSW Builder Licence No. 377506C
DPBA No. BUP4254863
© Levant Projects. All rights reserved.